Zoom Tech Ltd investigates all variances above 10 percent of the flexible budget. The flexible budget for
Fantastic news! We've Found the answer you've been seeking!
Question:
- Zoom Tech Ltd investigates all variances above 10 percent of the flexible budget. The flexible budget for direct labour is $50,000. The direct labour rate variance is $4 000 unfavourable, and the direct labour efficiency variance is $6,000 favourable.
Required:
Provide two possible explanations for each variance identified in this question