An assembly line with 30 activities is to be balanced. The total amount of time to complete

Question:

An assembly line with 30 activities is to be balanced.

The total amount of time to complete all 30 activities is 60 minutes. The longest activity takes 2.4 minutes and the shortest takes 0.3 minutes.

The line will operate for 480 minutes per day.

a. What are the maximum and minimum cycle times?

b. How much daily output will be achieved by each of those cycle times?