Can a project have two paths that are critical paths? Explain why or why not. Give an
Question:
Can a project have two paths that are critical paths? Explain why or why not. Give an example if possible.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 75% (12 reviews)
Yes there can be two or more critical paths A critical path is defined ...View the full answer
Answered By
Jonas Araujo
I have recently received the degree of PhD. In Physics by the Universidade Federal do Maranhão after spending a term in Durham University, as I have been awarded a scholarship from a Brazilian mobility program. During my PhD. I have performed research mainly in Theoretical Physics and published works in distinguished Journals (check my ORCID: https://orcid.org/0000-0002-4324-1184).
During my BSc. I have been awarded a scholarship to study for a year in the University of Evansville, where I have worked in detection-analysis of photon correlations in the the Photonics Laboratory. There I was a tutor in Electromagnetism, Classical Mechanics and Calculus for most of that year (2012).
I am very dedicated, honest and a fast learner, but most of all, I value a job well done.
5.00+
1+ Reviews
10+ Question Solved
Related Book For
Systems Analysis and Design in a Changing World
ISBN: 978-1305117204
7th edition
Authors: John W. Satzinger, Robert B. Jackson, Stephen D. Burd
Question Posted:
Students also viewed these Computer science questions
-
Now suppose that there are M paths between the server and the client. No two paths share any link. Path k (k = 1, . . . , M ) consists of N links with transmission rates Rk1, Rk2, .. . , RkN. If the...
-
Consider Figure 1.19(b). Now suppose that there are M paths between the server and the client. Nu two paths share any link. Path k (k = 1,...,M) consists of N links with transmission rates R k 1 , R...
-
1. In business process modeling notation, a gateway is like a fork in the road, allowing the flow to go one way or another. You can learn more about gateways in the Visible Analyst Glossary feature....
-
Concentric shells r = 20 cm and r = 30 cm are held at V = 0 and V = 50, respectively. If the space between them is filled with dielectric material ( = 3.10, a = 1012 S/m), find: (a) V, E, and D, (b)...
-
Biko owns a snowmobile manufacturing business, and Miles owns a mountain bike manufacturing business. Because each business is seasonal, their manufacturing plants are idle during their respective...
-
Gemini Ltd. has accounts receivable of $370,000 and an unadjusted credit balance in its allowance for doubtful accounts of $8,800 at March 31. The company's accounts receivable and percentage...
-
Solve Problem 13.48 using a forcing frequency \(\omega=10 \mathrm{rad} / \mathrm{s}\) instead of \(5 \mathrm{rad} / \mathrm{s}\). Data From Problem 13.48:- A single-degree-of-freedom system has a...
-
1. Estimate 3PARs equity value per share based on the assumptions and selected 3PAR data provided in Table. 2. Why is it appropriate to utilize at least a ten-year annual time horizon before...
-
BMX Company has one employee. FICA Social Security taxes are 6.2% of the first $137,700 paid to its employee, and FICA Medicare taxes are 1.45% of gross pay. For BMX, its FUTA taxes are 0.6% and SUTA...
-
Colfax Glassworks stock currently sells for $36 per share. One year ago the stock sold for $33.The company recently paid a $3 per share dividend. What was the rate of return for an investor in Colfax...
-
Discuss the difference between a PERT/CPM chart and a Gantt chart. List comparative advantages and disadvantages of each.
-
What is the difference between effort and duration in Microsoft Project?
-
West Coast Healthcare operates two medical groups, one in Seattle and one in San Francisco. The semi- annual bonus plan for each medical groups president has three components: a. Profitability...
-
The line chart shows the sales revenue with sales order month on the x axis and sales in amount of dollars in the y axis. The x axis ranges from May 2017 to November 2020 in increments of 6 months....
-
Business Formation" Please respond to the following, Use the Internet or Strayer online databases to research two (2) businesses that are formed differently (i.e., corporation, limited partnership,...
-
What did ferguson PD do to generate revenue in 2014?
-
The company EL REKETON, SA, requested a loan on March 16, 2022 for L. 2,100,000. with 12.30% annual interest, payable in installments every 4 months of L.350,000 as a capital payment plus the...
-
1. How do the risks associated with network systems compare with the risks associated with centralized IT functions? 2. What is the relationship between tolerable misstatement, inherent risk, and...
-
Is the weight of a system an extensive or intensive property?
-
Medi-Exam Health Services, Inc. (MEHS), located in a major metropolitan area, provides annual physical screening examinations, including a routine physical, EKG, and blood and urine tests. MEUS's...
-
Why do companies use colocation facilities?
-
List five issues that are important when considering an external hosting company.
-
Describe the primary factors that affect throughput for Internet systems.
-
ow do synergistic dynamics emerge within high-performance teams, and what role do diverse skill sets, complementary roles, and shared goals play in fostering collaborative innovation and collective...
-
Pietro Frozen Foods, Inc., produces frozen pizzas. For next year, Pietro predicts that 50,000 units will be produced, with the following total costs: Direct materials Direct labor Variable overhead...
-
You will complete two case studies over the course of the semester. These are to be completed individually. Each case study is found in the textbook and there are questions there to help guide your...
Study smarter with the SolutionInn App