Equipment ratings for the five-bus power system shown in Figure 7.15 are as follows: A three-phase short

Question:

Equipment ratings for the five-bus power system shown in Figure 7.15 are as follows:

image text in transcribed

A three-phase short circuit occurs at bus 5, where the prefault voltage is 15kV15kV. Prefault load current is neglected.

(a) Draw the positive-sequence reactance diagram in per unit on a 100MVA,15kV100MVA,15kV base in the zone of generator G2. Determine

(b) the Thévenin equivalent at the fault,

(c) the subtransient fault current in per unit and in kA rms,

(d) contributions to the fault from generator G2 and from transformer T2.