Open PowerWorld Simulator case Problem 11_24, which models the Example 6.9 with transient stability data added for

Question:

Open PowerWorld Simulator case Problem 11_24, which models the Example 6.9 with transient stability data added for the generators. Determine the critical clearing time (to the nearest 0.01 second) for a fault on the line between buses 4 and 5 at the bus 4 end which is cleared by opening the line.