Suppose that a lean work center is being operated with a lot size of 50 units. Assume

Question:

Suppose that a lean work center is being operated with a lot size of 50 units. Assume that 200 parts are demanded per hour and it takes three hours to circulate a container, including all setup, run, move, and idle time.
a. Calculate the number of kanban containers required.
b. What is the maximum inventory that will accumulate?
c. What can be done to reduce the inventory level? Suggest alternatives.