Table contains data for the installation of new equipment in a manufacturing process at your customers plant.

Question:

Table contains data for the installation of new equipment in a manufacturing process at your customer€™s plant. Your company is responsible for the project. Indirect costs are $10,000 per week, and a penalty cost of $10,000 per week will be incurred for every week the project is delayed beyond week 9.
a. What is the shortest time duration for this project regardless of cost?
b. What is the minimum total cost associated with completing the project in 12 weeks?
c. What is the total time of the minimum costschedule?
Table contains data for the installation of new equipment in
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations management processes and supply chain

ISBN: 978-0136065760

9th edition

Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra