Question

The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14.


a. What is the project’s duration if only normal times are used?
b. What is the minimum-cost schedule?
c. What is the critical path for the minimum-costschedule?