The BOM for product A is shown next and data
The BOM for product A is shown next and data from the inventory records are shown in the table. In the master production schedule for product A, the MPS quantity row (showing completion dates) calls for 250 units in week 8. The lead time for production of A is two weeks. Develop the materials requirements plan for the next eight weeks for Items B, C, and D.