The desired daily output for an assembly line is 360 units. This assembly line will operate 450 minutes per day. The following table contains information on this product’s task times and precedence relationships:

a. Draw the precedence diagram.
b. What is the workstation cycle time required to produce 360 units per day?
c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion.
d. What is the efficiency of your line balance, assuming it is running at the cycle time from part(b)?

  • CreatedApril 09, 2014
  • Files Included
Post your question