Question: The following four jobs must be processed in two processes

The following four jobs must be processed in two processes A and B. All jobs must go through process A first then process B. The process times are given below in minutes.


a. Determine the optimal order in which the job should be sequenced.
b. Schedule the jobs through the two processes and calculate the percent idle time for thisschedule.