Question: The following four jobs must be processed in two processes

The following four jobs must be processed in two processes A and B. All jobs must go through process A first then process B. The process times are given below in minutes.


a. Determine the optimal order in which the job should be sequenced.
b. Schedule the jobs through the two processes and calculate the percent idle time for thisschedule.
View Solution:


Sale on SolutionInn
Sales1
Views136
Comments
  • CreatedAugust 26, 2013
  • Files Included
Post your question
5000