The following information applies to Job 730 completed by Riverton Manufacturing Company during October 2017. The amount

Question:

The following information applies to Job 730 completed by Riverton Manufacturing Company during October 2017. The amount of labor cost for the job was $162,000. Applied overhead amounted to $230,000. The project was completed and delivered to Hudson Company at a contract price of $654,000. Riverton recognized a gross profit of $120,000 on the job.
Required
Determine the amount of raw materials used to complete Job 730.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Fundamental Managerial Accounting Concepts

ISBN: 978-1259569197

8th edition

Authors: Thomas Edmonds, Christopher Edmonds, Bor Yi Tsay, Philip Olds

Question Posted: