The following information is provided to you for each of five elements performed in building the Aviator

Question:

The following information is provided to you for each of five elements performed in building the Aviator model, a basic universal remote control.


The following information is provided to you for each of


(a) Calculate the normal time for each element.
(b) If the company uses a 15 percent allowance factor based on time worked, calculate the standard time for each element.
(c) Calculate the standard hourly output.
(d) Calculate the expected hourly output at 90 percent ofstandard.