The following list of jobs in a critical department includes estimates of their required times: a. Use
Question:
a. Use the shortest operation time rule to schedule these jobs.
What is the schedule?
What is the mean flow time?
b. The boss does not like the schedule in part (a). Jobs E and G must be done first, for obvious reasons. (They are already late.) Reschedule and do the best you can while scheduling Jobs E and G first and second, respectively.
What is the new schedule?
What is the new mean flowtime?