The following schedules (in hours) were prepared by the production manager of a metal shop. Note that

Question:

The following schedules (in hours) were prepared by the production manager of a metal shop. Note that ail jobs first go through cutting, then polishing.
The following schedules (in hours) were prepared by the production

Determine a sequence of jobs that will result in a shorter make-span.