The following table contains order-dependent setup times for four jobs. For safety reasons, job C cannot follow

Question:

The following table contains order-dependent setup times for four jobs. For safety reasons, job C cannot follow job A, nor can job A follow job C. Determine the processing sequence that will minimize the total setup time.
The following table contains order-dependent setup times for four jobs.