Question: The following table provides the crash data for the network

The following table provides the crash data for the network project described in Problem 12:


The normal activity times are considered to be deterministic and not probabilistic. Using the computer, crash the network to 26 weeks. Indicate how much it would cost the bank and then indicate the criticalpath.
View Solution: