The machining time per piece is 0.164 hours and the machine loading time is 0.038 hours. With

Question:

The machining time per piece is 0.164 hours and the machine loading time is 0.038 hours. With an Operator rate of $12.80 per hour and a machine rate of $14 per hour, calculate the optimum number of machines for lowest cost per unit of output.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Niebels Methods, Standards and Work Design

ISBN: 978-0073376318

13th edition

Authors: Andris Freivalds, Benjamin Niebel

Question Posted: