The Maser is a new custom-designed sports car. An analysis of the task of building the Maser reveals the following list of relevant activities, their immediate predecessors, and their duration:

(a) Draw a network diagram for the project.
(b) Mark the critical path and state its length.
(c) If the Maser had to be completed 2 days earlier, would it help to?
(i) Buy preassembled transmissions and drivetrains?
(ii) Install robots to halve engine-building time?
(iii) Speed delivery of special accessories by 3 days?
(d) How might resources be borrowed from activities on the noncritical path to speed activities on the criticalpath?