The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time

Question:

The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $ 10. There is a carrying cost of $ 0.01 per unit per week. Beginning inventory is 90 units.

The MRP gross requirements for Item A are shown here

Use the least total cost or the least unit cost lot sizing method to determine when and for what quantity the first order should bereleased.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations and Supply Chain Management

ISBN: 978-0078024023

14th edition

Authors: F. Robert Jacobs, Richard Chase

Question Posted: