Question: The operations manager of a large plant wishes to overhaul

The operations manager of a large plant wishes to overhaul a machine. After conducting a PERT/CPM analysis he has developed the following critical path.
1. Disassemble machine
2. Determine parts that need replacing
3. Find needed parts in inventory
4. Reassemble machine
5. Test machine
He has estimated the mean (in minutes) and variances of the completion times as follows.


Determine the mean and variance of the completion time of theproject.