The project described in tire following table and precedence network has just begun. It is scheduled to
Question:
a. if you were the manager of tills project, would you be concerned? Explain.
b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000?