Question: The table below shows the tasks required to assemble an

The table below shows the tasks required to assemble an aluminum storm door and the length of time needed to complete each task.
/

Suppose a cycle time is 90 seconds
(a) Compute the theoretical minimum number of workstations.
Work Station Task Selected
1 ........... A, B, C
2 ............ D, E, F, G, H (b) Compute the outputs. The maximum output?
The minimum output?


(c) Compute the efficiency. (Round your answer to 2 decimal places, the tolerance is+/-0.05.)