Question

The table below shows the tasks required to assemble an aluminum storm door and the length of time needed to complete each task.
/

Suppose a cycle time is 90 seconds
(a) Compute the theoretical minimum number of workstations.
Work Station Task Selected
1 ........... A, B, C
2 ............ D, E, F, G, H (b) Compute the outputs. The maximum output?
The minimum output?


(c) Compute the efficiency. (Round your answer to 2 decimal places, the tolerance is+/-0.05.)