The Tesla 6 is a new custom- designed sports car. An analysis of the task of building the Tesla 6 reveals the following list of relevant activities, their immediate predecessors, and their duration:

Draw a network diagram for the project.
Mark the critical path and state its length.
If the Tesla 6 had to be completed 2 days earlier, would it help to:
i) Buy preassembled transmissions and drivetrains?
ii) Install robots to halve engine- building time?
iii) Speed delivery of special accessories by 3 days?
How might resources be borrowed from activities on the non-critical path to speed activities on the criticalpath?