Question: Three Brothers Catering uses the high low method to predict

Three Brothers Catering uses the high- low method to predict its total overhead costs. Past records show that total overhead cost was $ 25,600 when 810 hours were worked and $ 27,700 when 910 hours were worked. If Three Brothers Catering has 835 hours scheduled for next month, what is the expected total overhead cost for next month?