Question

Twelve tasks, with times and precedence requirements as shown in the following table, are to be assigned to workstations using a cycle time of 1.5 minutes. Two heuristic rules will be tried: (1) greatest positional weight, and (2) most following tasks. In each case, the tiebreaker will be shortest processing time.

.:.
a. Draw the precedence diagram for this line.
b. Assign tasks to stations under each of the two rules.
c. Compute the percentage of idle time for each rule.