Two new software projects are proposed to a young, start-up company. The Alpha project will cost $150,000

Question:

Two new software projects are proposed to a young, start-up company. The Alpha project will cost $150,000 to develop and is expected to have annual net cash flow of $40,000. The Beta project will cost $200,000 to develop and is expected to have annual net cash flow of $50,000. The company is very concerned about their cash flow. Using the payback period, which project is better from a cash flow standpoint? Why?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project management the managerial process

ISBN: 978-0073403342

5th edition

Authors: Eric W Larson, Clifford F. Gray