Using the following project information The critical path is A-C-E-G-I-J. Calculate the probability that the project will
Question:
The critical path is A-C-E-G-I-J.
Calculate the probability that the project will be completed in 38 weeks.
Calculate the probability that the project will be completed in 42 weeks.
Transcribed Image Text:
Optimistic Time Estimate(weeks) Variance Expected Activity Most Pessimistic Immediate Likely Predecessor(s) Time Time Time Estimates (weeks) Estimates (weeks) (weeks) 1.000 6.00 none A 0.444 5.00 7.33 12 A 1.778 7.67 10 1.000 10.17 5 10 16 3.361 D,E 0.111 4.00 0.694 G 8. D,E 5.83 Н 10 0.694 6.33 11 1.000 8.00 3.00 3 3 Н. 0.000 6. 3. 3. 3.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 54% (11 reviews)
Path Expected Completion Time Variance 38 week zvalue ...View the full answer
Answered By
Abigael martinez
I have been a tutor for over 3 years and have had the opportunity to work with students of all ages and backgrounds. I have a strong belief that all students have the ability to learn and succeed if given the right tools and support. I am patient and adaptable, and I take the time to get to know each student's individual learning style in order to best support their needs. I am confident in my ability to help students improve their grades and reach their academic goals.
5.00+
1+ Reviews
10+ Question Solved
Related Book For
Methods of IT Project Management
ISBN: 978-1557536631
2nd edition
Authors: Jeffrey Brewer, Kevin Dittman
Question Posted:
Students also viewed these Managerial Accounting questions
-
Using the following project information The critical path is A-C-E-G-I-J. (a) Calculate the probability that the project will be completed in 38 weeks. P(project 38) = (b) Calculate the probability...
-
Using the follow gin project information The critical path is A-C-E-G-I-J. (a) Calculate the probability that the project will be completed in 38 weeks. (b) Calculate the probability that the project...
-
Using the following project information, calculate the variance for each of the project activities. Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Estimate (weeks) Estimates...
-
How to find the expected utility of profit under each alternative crop Table 1. Annual Returns to Cropping Alternatives ($ profit / acre) Outcome Worst Bad OK Good Great Probability 0.1 0.2 0.4 0.2...
-
A continuous cable of total length l is wrapped around the small pulleys at A, B, C, and D. If each spring is stretched a distance b, determine the mass M of each block. Neglect the weight of the...
-
Confirm that the below limit meets the conditions to apply l'Hpital's Rule and then solve the limit. Be sure to address these conditions in your explanation. Enter an exact numeric answer. lim In(x)...
-
Differentiate the cost and value drivers in a projects supply chain.
-
A stock's return has the following distribution: Calculate the stock's expected return, standard deviation, and coefficient of variation. Demand for the Probability of This Demand Occrring Rate of...
-
Consider one disk with 2000 cylinders, numbered 0 to 1 999. Assume the current position of head is at cylinder 500. The request queue is given as follows: 103, 80, 1400, 813, 1714, 748, 1500, 1100...
-
Kidd is a self-employed single taxpayer in 2022 that files Schedule C for his sole proprietorship. He pays for his own health insurance and the premiums are less than his net profits. Kidd will...
-
Oakley Company does not ring up sales taxes separately on the cash register. Total receipts for February amounted to $42,800. If the sales tax rate is 7%, what amount must be remitted to the state...
-
1. Activity based costing for selling and administrative expenses can also be beneficial in allocating expenses to various products. Which of the following is the best allocation base for help desk...
-
A diol (C8H18O2) does not react with periodic acid. Its 1H NMR spectrum contains three singlets at 1.2 (12 protons), 1.6 (4 protons), and 2.0 ppm (2 protons). What is the structure of this diol?
-
It was 2021, and the world was deep into the crisis of the COVID-19 (Corona Virus Disease) pandemic which had triggered a variety of challenges for organizations worldwide. Earlier in the year, a...
-
Abbott placed into service a flexible manufacturing cell costing $840,000 early this year. They financed $425,000 of the initial cost of the cell at 11% per year over 5 years. Gross income due to the...
-
6. Over the past five days, Stocks A and B performed as shown below Day % Ret A % Ret B 4 6 Irr -6 1 3 -5 2 1 -4 -3 -1 2 4 m 00 T -4 Find and interpret the correlation coefficient of returns.
-
Using the Threat and Hazard Identification and Risk Assessment (THIRA) identify a natural, technological, or human-caused hazard that has been or has the potential of being a threat to your...
-
Need help with the formula for the Return the Distributor Name if they sell online or selll over$1,000 of product, otherwise leave it blank. Return the Distributor Name if they sell online or sell...
-
Question for classroom or small-group discussion. Now that we have studied different kinds of costs and the systems used to accumulate them, lets think about how these concepts might apply in the...
-
A new car sold for $31,000. If the vehicle loses 15% of its value each year, how much will it be worth after 10 years?
-
The concentration of an active ingredient in the output of a chemical reaction is strongly influenced by the catalyst that is used in the reaction. It is felt that when catalyst A is used the...
-
From the information in Review Exercise 8.70 compute (assuming B = 65%) P(XB > 70).
-
Given a normal random variable X with mean 20 and variance 9, and a random sample of size n taken from the distribution, what sample size n is necessary in order that P(19.9 < X < 20.1) = 0.95?
-
A 7 5 kg cliff - diver is falls from a height through the air head, diving towards the water. The drag coefficient for the diver is 0 . 8 3 and the area of the descending diver is 0 . 2 1 m ^ 2 ....
-
In the automobile industry, the dimensionless drag coefficient and the area of the vehicle are often combined into one variable - the drag area whereby the drag area is the product of the...
-
When you drop 10 pebbles into the well, you record the times for hearing the splash as 2.94 s, 3.11 s, 3.12 s, 2.97 s, 3.12 s, 2.97 s, 3.06 s, 3.21 s, 3.37 s, and 3.53 s. (a) Find the average time...
Study smarter with the SolutionInn App