Wahr Corporation bases its predetermined overhead rate on the es
Wahr Corporation bases its predetermined overhead rate on the estimated labor hours for the upcoming year. At the beginning of the most recently completed year, the company estimated the labor hours for the upcoming year at 32,000. The estimated variable manufacturing overhead was $7.17 per labor hour and the estimated total fixed manufacturing overhead was $584,320. The actual labor hours for the year turned out to be 33,300.

Required: Compute the company's predetermined overhead rate for the recently completed year.