You are given the following information about a project consisting
You are given the following information about a project consisting of six activities:
(a) Construct the project network for this project.
(b) Find the earliest times, latest times, and slack for each activity. Which of the paths is a critical path?
(c) If all other activities take the estimated amount of time, what is the maximum duration of activity D without delaying the completion of the project?