You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days
Question:
The network for this project is given below.
The indirect costs for the project are determined on a daily duration basis and are given below:
Total indirect costs for 16 days of project duration: $ 600
Total indirect costs for 15 days of project duration: $ 400
Total indirect costs for 14 days of project duration: $ 200
Total indirect costs for 13 days of project duration: $ 100
At what project duration do we achieve the lowest total project cost (i.e., direct plus indirect costs)?
(a) 16 days
(b) 15 days
(c) 14 days
(d) 13 days