Question

You have estimated the following cash flows on a project:
Year Cash Flow to Equity ($)
0 ............. −5,000,000
1 ............. 4,000,000
2 ............. 4,000,000
3 ............. −3,000,000
Plot the NPV profile for this project. What is the IRR? If the cost of equity is 16%, would you accept this project?