You have just been notified via fax that the lead
You have just been notified via fax that the lead time for component G of product A (problem 14.15 and figure 14.16) has been increased to 4 weeks.
(a) Which items have changed and why?
(b) What are the implications for the production plan?
(c) As production planner, what can youdo?