If activity A is not on the critical path, then the slack for A will equal a.
Question:
If activity A is not on the critical path, then the slack for A will equal
a. LF - EF.
b. EF - ES.
c. 0.
d. all of the above.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 50% (2 reviews)
If activity A is not on the critical path then the sl...View the full answer
Answered By
Ashington Waweru
I am a lecturer, research writer and also a qualified financial analyst and accountant. I am qualified and articulate in many disciplines including English, Accounting, Finance, Quantitative spreadsheet analysis, Economics, and Statistics. I am an expert with sixteen years of experience in online industry-related work. I have a master's in business administration and a bachelor’s degree in education, accounting, and economics options.
I am a writer and proofreading expert with sixteen years of experience in online writing, proofreading, and text editing. I have vast knowledge and experience in writing techniques and styles such as APA, ASA, MLA, Chicago, Turabian, IEEE, and many others.
I am also an online blogger and research writer with sixteen years of writing and proofreading articles and reports. I have written many scripts and articles for blogs, and I also specialize in search engine
I have sixteen years of experience in Excel data entry, Excel data analysis, R-studio quantitative analysis, SPSS quantitative analysis, research writing, and proofreading articles and reports. I will deliver the highest quality online and offline Excel, R, SPSS, and other spreadsheet solutions within your operational deadlines. I have also compiled many original Excel quantitative and text spreadsheets which solve client’s problems in my research writing career.
I have extensive enterprise resource planning accounting, financial modeling, financial reporting, and company analysis: customer relationship management, enterprise resource planning, financial accounting projects, and corporate finance.
I am articulate in psychology, engineering, nursing, counseling, project management, accounting, finance, quantitative spreadsheet analysis, statistical and economic analysis, among many other industry fields and academic disciplines. I work to solve problems and provide accurate and credible solutions and research reports in all industries in the global economy.
I have taught and conducted masters and Ph.D. thesis research for specialists in Quantitative finance, Financial Accounting, Actuarial science, Macroeconomics, Microeconomics, Risk Management, Managerial Economics, Engineering Economics, Financial economics, Taxation and many other disciplines including water engineering, psychology, e-commerce, mechanical engineering, leadership and many others.
I have developed many courses on online websites like Teachable and Thinkific. I also developed an accounting reporting automation software project for Utafiti sacco located at ILRI Uthiru Kenya when I was working there in year 2001.
I am a mature, self-motivated worker who delivers high-quality, on-time reports which solve client’s problems accurately.
I have written many academic and professional industry research papers and tutored many clients from college to university undergraduate, master's and Ph.D. students, and corporate professionals. I anticipate your hiring me.
I know I will deliver the highest quality work you will find anywhere to award me your project work. Please note that I am looking for a long-term work relationship with you. I look forward to you delivering the best service to you.
3.00+
2+ Reviews
10+ Question Solved
Related Book For
Quantitative Analysis For Management
ISBN: 213168
12th Edition
Authors: Barry Render ,Ralph M. Stair ,Michael E. Hanna
Question Posted:
Students also viewed these Business questions
-
Kindly research on the following topic:AgriTech in USA competitiors with their price of product, elecreuticity, the overall product and its price.
-
Saying to yourself I will perform poorly on this test is an example of ________. a self-imposed prophecy a self-motivated prophecy a debilitative sense of self an unhealthy self-concept None of the...
-
Jane Pearman bought a house in Barrie for $850,000 that includes her down payment. To help finance the purchase she took out a mortgage at 7.245 % compounded semi-annually that will be repaid with...
-
Write the boldfaced numbers in each problem in scientific notation. The largest of the 50 United States is Alaska, with land area of about 365,482,000 acres, while the smallest is Rhode Island, with...
-
Explain how to use the inverse of a matrix to solve a system of linear equations.
-
Use a graphing calculator to graph the equation in the standard window. y = 2 - x 2
-
Are there any voting rights attached to a tracking stock?
-
Swift Manufacturing must choose between two asset purchases. The annual rate of return and the related probabilities given in the following table summarize the firm's analysis to this point. a. For...
-
Find the derivative of the following function. 1 8 2s 4 5s dr ds 11
-
If a project is to be crashed at the minimum possible additional cost, then the first activity to be crashed must be a. on the critical path. b. the one with the shortest activity time. c. the one...
-
If the project completion time is normally distributed and the due date for the project is greater than the expected completion time, then the probability that the project will be finished by the due...
-
For each of the following situations, identify (1) the case as either (a) a present or a future value and (b) a single amount or an annuity, (2) the table you would use in your computations (but do...
-
Write down the Gromic-Lamb type differential equation of motion for the incompressible viscous fluid, and explain the physical meaning of each item?
-
The reading of the barometer on a certain day is 101.672 kPa. Try to calculate the force in N per 1 m2 of the atmospheric pressure.
-
The volume of a gas tank is 27.1 m3, stored with compressed air. Given that the temperature of the air in the tank is 303 K and the pressure is 127.825 kPa, what is the mass of the compressed air in...
-
The volume of a gas storage tank is 6 m3, which stores 48.1 kg of air. Try to determine the density of the air in the air storage tank.
-
A vertical clean glass manometer tube has an inside diameter of 1 mm. When pressure is applied, the water at 20 C rises to a height of 25 cm. After correcting the surface tension, estimate the...
-
You are a salesperson for Proctor and gamble selling Tide detergent. List and describe in detail the seven tasks that you or any other salesperson must perform in your profession. Relate these tasks...
-
In your readings, there were many examples given for nurturing close family relationships in this ever-evolving technological society we live in Based upon your readings and research describe three...
-
Why would a marketing manager prefer to sell a product that has no close substitutes? Are high profits almost guaranteed?
-
If a manufacturers well-known product is sold at the same price by many retailers in the same co m munity, is this an example of pure competition? When a community has many small grocery stores, are...
-
List three products that are sold in purely competitive markets and three that are sold in monopolistically competitive markets. Do any of these products have anything in common? Can any...
-
Select the most correct answer from the material provided in this course that finishes the collowing statement. An option for temporary leased space is: A. working outdoors near the damaged facility...
-
3 1 pts Ancient Grains, Inc. issued a 4 month note in the amount of $500,000 on October 1, 2021 with an annual rate of 5%. What amount of interest has accrued as of December 31, 2021? Note: your...
-
When calculating the weighted average number of ordinary outstanding shares during the period, which of the following is treated as if it were outstanding since the beginning of the year? I....
Study smarter with the SolutionInn App