39. Use the following data and calculate the effort and duration required for every task, considering...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
39. Use the following data and calculate the effort and duration required for every task, considering the following constraints: Task Design Write High Level DD Review High Level DD Level DD 1. Every review "meeting" task shall be carried by 5 engineers including ONE of the author(s) 2. Every review "preparation task shall be carried by 4 engineers excluding the author(s) Preparation for High 3. Any "Rework" task can be executed by one or al authors of the original task 4. Clearly state how many headcounts will work on authoring/writing the artifact Review Meeting Rework Write Low Level DD Level DD Review Low Level DD Preparation for Low Rework Review Meeting Effort Duration Amount of Work 320 pages 190 defects. 225 pages 143 defects Productivity Rate Spoges/Hour 5 pages/Hour 5 pages/Hour 5 defects/Hour 1 page/Hour 5 pages/Hour 5 pages/Hour 5 defects/Hour 202 39. Use the following data and calculate the effort and duration required for every task, considering the following constraints: Task Design Write High Level DD Review High Level DD Level DD 1. Every review "meeting" task shall be carried by 5 engineers including ONE of the author(s) 2. Every review "preparation task shall be carried by 4 engineers excluding the author(s) Preparation for High 3. Any "Rework" task can be executed by one or al authors of the original task 4. Clearly state how many headcounts will work on authoring/writing the artifact Review Meeting Rework Write Low Level DD Level DD Review Low Level DD Preparation for Low Rework Review Meeting Effort Duration Amount of Work 320 pages 190 defects. 225 pages 143 defects Productivity Rate Spoges/Hour 5 pages/Hour 5 pages/Hour 5 defects/Hour 1 page/Hour 5 pages/Hour 5 pages/Hour 5 defects/Hour 202
Expert Answer:
Answer rating: 100% (QA)
Task 1 Design artifact 1 Authoring headcount 2 engineers Authoring effort 2 engineers x 5 days 10 persondays Review meeting 5 engineers x 2 hrs 10 per... View the full answer
Related Book For
Systems Analysis and Design in a Changing World
ISBN: 978-1305117204
7th edition
Authors: John W. Satzinger, Robert B. Jackson, Stephen D. Burd
Posted Date:
Students also viewed these programming questions
-
Forever Old Thrift Shop is considering renovating the entire store shopping area to attract more customers. The cost of the renovation is $10,000. The net cash flows resulting from the investment are...
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
Read the case study "Southwest Airlines," found in Part 2 of your textbook. Review the "Guide to Case Analysis" found on pp. CA1 - CA11 of your textbook. (This guide follows the last case in the...
-
When the freed slave saw the real physical object? A) He was perplexed by the object when he was told what they were B) He was dazzled by the light C) He didn't believe what he was told D) all adove...
-
Develop an understanding on the following topics in order to establish a breif discuss. The difference between book value and market value The difference between accounting income and cash flow The...
-
How can we use dramatic and formal elements to define and organize our game components?
-
_____________ is a pictorial display of personal relationship among related or unrelated parties. a. Timeline b. Entity charts c. Genogram d. Graphology e. Full-inclusion
-
Wild Expansion Co. acquired the following assets in exchange for various nonmonetary assets. 2011 Mar. 15 Acquired from another company a large lathe in exchange for three small lathes. The small...
-
What is the Future Value of 1000$ in 2 years at a rate of10%? 2 answers
-
I. Efficient Two Asset Portfolios Assume that the expected return on asset 1 is 5% and the expected return on asset 2 is 4%. The standard deviation of asset 1 is 3.0% and 1.5% for asset 2. Assume the...
-
. Indicate whether a debit or credit decreases the normal balance of each of the following accounts. X Answer is complete but not entirely correct. Decrease Normal Balance a. Trucks Debit X b....
-
Globe Inc. is a distributor of DVDs. DVD Mart is a local retail outlet which sells blank and recorded DVDs. DVD Mart purchases DVDs from Globe at $29.00 per DVD; DVDs are shipped in packages of 65....
-
Following is information on an investment in a manufacturing machine. The machine has zero salvage value. The company requires a 9 % return from its investments. Initial investment $ ( 2 6 0 , 0 0 0...
-
4.44/5 E : According to www.money-zine.com, the average FICO score in the United States was around 692 in December 2011. Suppose the following data represent the credit scores of 22randomly selected...
-
The income statement for the Bramble Discount Retail Company for the year ended December 3 1 2 0 2 5 appears below. Sales revenue $ 6 1 9 , 0 0 0 Cost of goods sold 3 6 0 , 4 2 0 Gross profit 2 5 8 ,...
-
Data was collected for 300 fish from the North Atlantic. The length of the fish (in mm) is summarized in the GFDT below. Lengths (mm) Frequency 40 - 41 1 42 - 43 16 44 - 45 71 46 - 47 108 48 - 49 83...
-
A B C D INSTRUCTIONS FOR THIS ASSIGNMENT ARE IN THE BUDGET CASE DETAILS DOCUMENT IN BRIGHTSPACE. You started your first job post-college at ABC Financial in Cleveland earning $60,000 per year. Using...
-
Given find the value of k. es 1 e kx dx = 1 4'
-
What is the difference between the project iteration schedule and the detailed work schedule?
-
Develop a storyboard that encompasses the following sample dialog. The system supports rental and download of movies or television shows to a computer or digital video recording and playback device....
-
List and briefly describe the three elements of the fraud triangle. Over which element can a system designer exercise the greatest control?
-
Imagine that you have \($10,000\) to invest. Use a newspaper, the Internet, or other source to select a mutual fund. Use the same source to fi nd out how much gold you could buy for \($10,000\)....
-
Animation art, hand-painted images from which cartoons used to be made, is a popular collectible.
-
The PBS television program, Antiques Roadshow, has generated enormous interest among viewers to find out the value of the furniture, art, jewelry, and collectibles they own.
Study smarter with the SolutionInn App