Suppose two new services, denoted A and B, are being introduced and learning curves are being used to estimate the time to complete these services in the future.
a) For service A, if the first service took 12 minutes and the 10th service took 9 minutes, then what is the learning rate r?
b) For service B, suppose the learning rate is 90%. If the first service for B took 8 minutes, then how long would the 20th service take?