The Widget Maker Company is bidding for a new job that requires building four widget prototypes....
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
The Widget Maker Company is bidding for a new job that requires building four widget prototypes. The company has never built the particular widget before, but its experts believe that its designers and workers will be able to pick it up with a learning rate of 80%. The activity of designing and building prototypes will gain from this learning rate for at least five cycles. The proposal team has come up with the following action plan and effort estimates for producing the four units. S. No. Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Effort in hrs Precedence 36 18 Concept development Design framework Design and build first prototype Ship to customer Analyze feedback Design and build second prototype Ship to customer Analyze feedback Design and build third prototype Ship to customer Analyze feedback Design and build final prototype 46.1 Ship to customer 3.6 Update customer design knowledge base 18 72 3.6 14.4 57.6 3.6 14.4 50.6 3.6 14.4 1FS 2FS 3FS 4FS+2 weeks lag 3FS 6FS 7FS+2 weeks lag 5FS, 6FS 9FS 10FS+2weeks lag 8FS, 9FS 12FS 11FS, 13FS The company plans its work assuming a 90% efficiency of its staff members. Task 2, Design framework, and Task 14, Update design knowledge base, require an expert designer who is available only 50% of the time due to other commitments. The company has an average labor rate of $50/hour. The benefit rate is 30%. Its overhead costs are 50% and its profit margin is 20%. The project plans are to be developed assuming 8 hours per working day and 5 working days per week. A. Provide a table with estimated durations for each task taking efficiency and availability in consideration where applicable. Please round to the nearest tenth of an hour. (30 points) HINT: provide a table with a column for allocated hr (efficiency) and a column for total task duration hr for each task. B. What is the total project duration in calendar weeks and completion date that the company should propose? Assume a start date of Monday, 6 February 2023, and that the company believes its estimates already are generous and no additional time buffer is needed. (10 points) C. What is the amount that the company should bid for this project? (10 points) The Widget Maker Company is bidding for a new job that requires building four widget prototypes. The company has never built the particular widget before, but its experts believe that its designers and workers will be able to pick it up with a learning rate of 80%. The activity of designing and building prototypes will gain from this learning rate for at least five cycles. The proposal team has come up with the following action plan and effort estimates for producing the four units. S. No. Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Effort in hrs Precedence 36 18 Concept development Design framework Design and build first prototype Ship to customer Analyze feedback Design and build second prototype Ship to customer Analyze feedback Design and build third prototype Ship to customer Analyze feedback Design and build final prototype 46.1 Ship to customer 3.6 Update customer design knowledge base 18 72 3.6 14.4 57.6 3.6 14.4 50.6 3.6 14.4 1FS 2FS 3FS 4FS+2 weeks lag 3FS 6FS 7FS+2 weeks lag 5FS, 6FS 9FS 10FS+2weeks lag 8FS, 9FS 12FS 11FS, 13FS The company plans its work assuming a 90% efficiency of its staff members. Task 2, Design framework, and Task 14, Update design knowledge base, require an expert designer who is available only 50% of the time due to other commitments. The company has an average labor rate of $50/hour. The benefit rate is 30%. Its overhead costs are 50% and its profit margin is 20%. The project plans are to be developed assuming 8 hours per working day and 5 working days per week. A. Provide a table with estimated durations for each task taking efficiency and availability in consideration where applicable. Please round to the nearest tenth of an hour. (30 points) HINT: provide a table with a column for allocated hr (efficiency) and a column for total task duration hr for each task. B. What is the total project duration in calendar weeks and completion date that the company should propose? Assume a start date of Monday, 6 February 2023, and that the company believes its estimates already are generous and no additional time buffer is needed. (10 points) C. What is the amount that the company should bid for this project? (10 points)
Expert Answer:
Related Book For
Posted Date:
Students also viewed these general management questions
-
3 4 5 6 7 8 9 10 11 12 13 A 14 Cost of the Asset 15 Life of the Asset in Years 16 Book Value of the Asset after 5 years 17 Depreciable Basis 18 Yearly depreciation 19 After tax Salvage Value in year...
-
Year 1 2 3 4 5 6 7 A coal mining company is expanding its existing operation. The company expects that it will experience an increasing stripping ratio scenario in the expansion area, and with...
-
A 1 defects size B D E 88888888888888888888888888 2 21 3 24 4 16 5 12 6 15 7 5 8 28 9 20 10 31 11 25 12 20 13 24 14 16 15 19 16 10 17 17 18 13 19 22 20 18 21 39 22 30 23 24 24 16 25 19 26 17 27 15...
-
A solid conducting cylinder of radius 0.1 m and mass of 4 kg rests on horizontal conducting rails (Figure). The rails, separated by a distance a?= 0.4 m, have a rough surface so the cylinder rolls...
-
One subunit of Freeway Sports Company had the following financial results last month: Requirements 1. Complete the performance evaluation report for this subunit (round to two decimal places). 2....
-
Consider the data set of oil well drilling costs given in DS 12.2.1. (a) What is the standard error of ^1? (b) Construct a two-sided 95% confidence interval for the slope parameter 1. (c) Test the...
-
On March 15, 2017, Hunt Brands, a U.S. company, purchased merchandise from a South African company at a price of R1,000,000, payable in two months in rands. To hedge its exposed liability position,...
-
The Harriet Hotel in downtown Boston has 100 rooms that rent for $150 per night. It costs the hotel $30 per room in variable costs (cleaning, bathroom items, etc.) each night a room is occupied. For...
-
Consider the following data for stocks and bonds in the scenario analysis and a portfolio with weights of 50% in stocks and 50% in bonds. Rate of Return Scenario Probability Stocks Bonds Seve...
-
In the circuit of Fig. 5.59 , calculate v o of v s = 2 V. 8 k2 2 k2 4 k2 4 k2 Vo Vs (+I) + I
-
John had $50 in total. He spent $10.50 to purchase a snack and $20.75 to purchase a lunch. How much amount left with him. Print remaining amount in US and German locale Number format.
-
To maintain independence, the data administrator must hold a senior position within the organizational hierarchy of the information systems function. Briefly explain.
-
What impact might the existence of end-user computing in an organization have on the roles of the data administrator and the database administrator?
-
Briefly explain the nature of metadata. Why is it critical that a database management system have strong capabilities for defining metadata?
-
Briefly explain the nature and functions of a data repository system. What is the relationship between a data repository system and the database definition?
-
How can a centralized database definition and a data repository system enhance control over the systems development process?
-
3. Based on the process mapped and described in the question 2, document or propose applicable analytic techniques to be used in the documentation and analysis of the process. Propose specific...
-
If someone's Z-score for a variable was 0.67. Their score is a significant extreme score. Their score is not significant. O Their score is slightly above average. O Their score is an outlier.
-
People like to have a stable living standard from one year to the next. Yet studies show that the level of consumption drops suddenly, predictably, and significantly at retirement (contrary to Figure...
-
Consider a bond with a face value of $1000 and a coupon of $100. Suppose the interest rate is 10 percent. Does the PDV of the promised payments depend on the bond's maturity? Why or why not? Think...
-
Suppose a single monopolist controls the market for Coke and Pepsi in Worked-Out Problem 19.2. If the monopolist sets the same price for Coke and Pepsi, what price would maximize its profit? How does...
-
The trial balance of Jeremina plc as at 31 March 2002 is as follows: (i) Stock of finished goods on 31 March 2002 163,000. (ii) Motor expenses and depreciation on motors to be apportioned:...
-
You are Br erired: with the following information relating to Plott plc for the year to 31 March 2011: Additional information: 1. The above information has been obtained after the compilation of the...
-
The following information has been extracted from the books of Quire plc as at 30 September 2011. The following additional information is to be taken into account: 1. Stocks at 30 September 2011 were...
Study smarter with the SolutionInn App