WBS Scheduled Start Budget Cost (Planned Value) Actual Cost Started Completed Hours Cost Per Hour Cost Hours
Fantastic news! We've Found the answer you've been seeking!
Question:
WBS | Scheduled Start | Budget Cost (Planned Value) | Actual Cost | Started | Completed | ||||
Hours | Cost Per Hour | Cost | Hours | Cost Per Hour | Cost | ||||
Clear Site | Monday Week 1 | 16 | $90 | $1,440 | 18 | $90 | $1,620 | Yes | Yes |
Dig Hole | Wednesday Week 1 | 8 | $180 | $1,440 | 9 | $180 | $1,620 | Yes | Yes |
Smooth hole | Thursday week 1 | 12 | $80 | $960 | 11 | $80 | $880 | Yes | Yes |
Install Pool | Monday Week 2 | 14 | $120 | $1,680 | 11 | $120 | $1,320 | Yes | Yes |
Install Pipes | Wednesday Week 2 | 12 | $80 | $960 | 14 | $80 | $1,120 | Yes | Yes |
Install Equipment | Friday Week 2 | 8 | $120 | $960 | No | No | |||
Install Paving | Monday Week 3 | 24 | $100 | $2,400 | No | No | |||
Landscape | Thursday Week 3 | 16 | $75 | $1,200 | No | No | |||
Total | 110 | $11,040 | 63 | $6,560 |
- What is the earned value (EV) for the project?
- What is the planned value (PV) for the project?
- What is the budget at completion (BAC)?
- What is Cost Variance (CV) for the project?
- What is the Schedule variance (SV) for the project?
- What is the cost performance index (CPI) for the project?
- What is the Schedule performance index (SPI) for the project?
- What is the estimate to complete (ETC) for the project predicting that the variance will continue?
- What is the estimated cost at completion (EAC) predicting that the variance will continue?