1. Why did the trial court grant the plaintiff’s summary judgment motion and order reformation in this case?
2. What is the difference between reformation and rescission of a contract?
3. Could Ronlee have rescinded the contract?

Per Curiam
The threshold question presented is whether the successful bidder for a government road construction contract is entitled to reformation of the contract to increase the price by $317,463 based on a unilateral mistake, after the competing bids are all opened, where the new contract price would still be lower than the second lowest bid.