A certification program consists of a series of activities that must be accomplished in a certain order.
Question:
(a) Develop a project network for the certification program.
(b) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the total program completion time and the critical path(s).
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Managerial Decision Modeling With Spreadsheets
ISBN: 9780136115830
3rd Edition
Authors: Nagraj Balakrishnan, Barry Render, Jr. Ralph M. Stair