A production lot of 25 units required 103.6 hours of effort. Accounting records show that the first

Question:

A production lot of 25 units required 103.6 hours of effort. Accounting records show that the first unit took 7 hours. What was the learning rate?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management A Managerial Approach

ISBN: 978-0470533024

8th edition

Authors: Jack R. Meredith, Samuel J. Mantel Jr.

Question Posted: