A system consists of two power plants that must deliver loads over a transmission network. The costs
Question:
F1 = 2p1 + 2
F2 = 10p2
Where p1 and p2 = power produced by each plant. The losses of power due to transmission L are given by
L1 = 0.2p1 + 0.1p2
L2 = 0.2p1 + 0.5p2
The total demand for power is 30 and p1 must not exceed 42. Determine the power generation needed to meet demands while minimizing cost using an optimization routine such as those found in, for example, Excel, MATLAB software, and IMSL.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Numerical Methods For Engineers
ISBN: 9780071244299
5th Edition
Authors: Steven C. Chapra, Raymond P. Canale
Question Posted: