Aerobatic, Inc. custom designs and manufactures light aircraft. The activities involved in this process are summarized in
Question:
Aerobatic, Inc. custom designs and manufactures light aircraft. The activities involved in this process are summarized in the following table.
a. Draw the activity network for this problem.
b. Create a spreadsheet to calculate and summarize the earliest and latest start and finish times, the slack for each activity, and the critical activities.
c. What is the earliest this project can be finished?
d. Use Microsoft Project to verify the critical path for thisproject.