After graduation, you and several of your friends decide to start a new software company. As the
Question:
You have identified several activities that must take place before this “burn-in” process is ready to use:
a. Draw the project network and calculate all ES, EF, LS, and LF times.
b. Every week of delay in the project costs your company $3,000. Suppose you know the following:
(1) Activity G can be crashed by 1 week, at a cost of $1,500;
(2) Activity F can be crashed by 1 week, at a cost of only
$50; and
(3) Activity H can be crashed by 1 week, at a cost of $2,000. Should you try to crash the project? If not, why not? If so, how much money will the company save?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Introduction to Operations and Supply Chain Management
ISBN: 978-0132747325
3rd edition
Authors: Cecil B. Bozarth, Robert B. Handfield
Question Posted: