Assume the following information: Probability of Failure Consequences of Failure Maturity = .3 ..Cost = .1 Complexity
Question:
Probability of Failure Consequences of Failure
Maturity = .3 ……………………………………..Cost = .1
Complexity = .3 ………………………………….Schedule = .7
Dependency = .5 …………………………………Performance = .5
Calculate the overall risk factor for this project. Would you assess this level of risk as low, moderate, or high? Why?