Best Bathware Company manufactures faucets in a small manufacturing facility. The faucets are made from zinc. Manufacturing
Question:
Standard wage per hr. ............. $14.60
Standard labor time per faucet ......... 15 min
Standard number of lbs. of zinc ....... 1.6 lbs
Standard price per lb. of zinc ........ $11.50
Actual price per lb. of zinc ......... $11.75
Actual lbs. of zinc used during the week ... 12,400 lbs.
Number of faucets produced during the week .... 7,500
Actual wage per hr. ............. $15.00
Actual hrs. per week ........... 1,800 hrs.
Instructions
Determine
(a) The standard cost per unit for direct materials and direct labor;
(b) The price variance, quantity variance, and total direct materials cost variance; and
(c) The rate variance, time variance, and total direct labor cost variance.