Coleman Rich, Ltd., has received the following orders: Period 1 2 3 4 5 6 7 8

Question:

Coleman Rich, Ltd., has received the following orders:
Period 1 2 3 4 5 6 7 8 9 10
Order size 60 30 10 40 70 10 40 30 40 0
The entire fabrication for these units is scheduled on one machine. There are 2,250 usable minutes in a week, and each unit will take 65 minutes to complete. Develop a capacity plan, using lot split-ting, for the 10- week time period.