Consolidated Minerals (CM) owns the rights to extract minerals from beach sands on Fraser Island. CM has

Question:

Consolidated Minerals (CM) owns the rights to extract minerals from beach sands on Fraser Island. CM has costs in three areas:

a. Payment to a mining subcontractor who charges $80 per tonne of beach sand mined and returned to the beach (after being processed on the mainland to extract three minerals: ilmenite, rutile, and zircon).

b. Payment of a government mining and environmental tax of $50 per tonne of beach sand mined.

c. Payment to a barge operator. This operator charges $150,000 per month to transport each batch of beach sand—up to 100 tonnes per batch per day—to the mainland and then return to Fraser Island (that is, 0 to 100 tonnes per day = $150,000 per month; 101 to 200 tonnes per day = $300,000 per month, and so on).

Each barge operates 25 days per month. The $150,000 monthly charge must be paid even if fewer than 100 tonnes are transported on any day and even if CM requires fewer than 25 days of barge transportation in that month.

CM is currently mining 180 tonnes of beach sands per day for 25 days per month.

REQUIRED

1. What is the variable cost per tonne of beach sand mined? What is the fixed cost to CM per month?

2. Plot a graph of the variable costs and another graph of the fixed costs of CM. Is the concept of relevant range applicable to your graphs? Explain.

3. What is the unit cost per tonne of beach sand mined (a) if 180 tonnes are mined each day and (b) if 220 tonnes are mined each day? Explain the difference in the unit-cost figures.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Cost Accounting A Managerial Emphasis

ISBN: 978-0133392883

6th Canadian edition

Authors: Horngren, Srikant Datar, George Foster, Madhav Rajan, Christ

Question Posted: