Dvorak Company produced 1,000 units of product that required three standard hours per unit. The standard fixed

Question:

Dvorak Company produced 1,000 units of product that required three standard hours per unit. The standard fixed overhead cost per unit is $ 0.60 per hour at 3,500 hours, which is 100% of normal capacity. Determine the fixed factory overhead volume variance.