Lead time for one of your fastest-moving products is 21 days. Demand during this period averages 100

Question:

Lead time for one of your fastest-moving products is 21 days. Demand during this period averages 100 units per day.
(a) What would be an appropriate reorder point?
(b) How does your answer change if demand during lead time doubles?
(c) How does your answer change if demand during lead time drops in half?